|
HOOKSETT
Hooksett to vote again on school budget
By Devon Cormier
Staff Writer
Hooksett will vote again on
the school district’s operating
budget, but will wait until next
year to decide what happens
with almost $1million left over
from school construction projects.
Fail, pass, fail again
Arevelation spurred Hooksett
School District Moderator
David Hess to call the Secretary
of State after the Tuesday,
March 8, when he questioned
the need for a two-thirds majority
on the leftover bond money.
If only a three-fifths majority
were necessary, the 354-181
vote would have been enough
for it to pass.
School Board Chairman Jim
Sullivan said Hess was told the
article had passed, not failed as
was the previous determination,
during his phone conversation
with the Secretary of State.
However, right before a petitioned
recount aimed at bolstering
the numbers of the failed
operating budget on Tuesday,
March 16, school officials were
told that a new bond may pass
by a three-fifths vote but the
change in use of an existing
bond must pass by two-thirds,
as previously thought, failing
the article again.
The recounted vote for the
use of the almost $1 million to
fix up the Underhill School
came in at 360-184, just a few
votes under the requirement for
a two-thirds vote. Initially the
article failed 354-181, which is
66.1 percent of the vote instead
of the 66.7 percent required,
almost the same as the recount
percentages.
Sullivan said the confusion
began when officials learned
that official ballot voting, commonly
called SB2, which the
school district operates under,
only requires a three-fifths vote
to pass a new bond. Old Town
Meeting style voting always
requires a two-thirds majority.
Regardless, Sullivan said the
school district will hold onto the
money and vote on it again next
year, because it does not return
to the general fund.
Repairs at Underhill would
have included the heating and
ventilation system, asbestos
removal, a sprinkler system, tile
and floor replacements, electrical
work and a roof upgrade
among other things. The repairs
were expected to cost between
$700,000 and $900,000 and the
remainder of the money would
go to repairs at the SAU building.
Budget recount
The two recounts on March
16 also proved the almost $21.7
million school operating budget
failed by a 265-270 simple
majority vote. The vote was initially
counted as 261 yes to 268
no.
School officials are now
researching cutting the budget
down and voting again to avoid
a default budget, which was calculated
at about $550,000 less
than the proposed budget. The
school district is facing its second
default budget in two years.
“We are considering reducing
the amount for an additional bus
and cutting the advanced learning
position,” Sullivan said.
“That would cut a little under
$100,000 and then we would go
back to the budget committee,
have another budget hearing
and then another whole day of
voting.”
Sullivan said the process is
allowed under the official ballot
law form of voting. This would
push voting to around May.
School officials voted to move
forward with a revote at the
March 16 recount.
Hooksett votes on town candidates
and warrants May 10.
|